Project Details
Many clients contact us for our tank decommissioning services. Often the removal of a tank isn't viable or cost effective. If there are no immediate plans for building works or to recommission the land where your underground tank is, decommissioning and tank filling is a great, viable option.
For this client, they didn't want the tank removed and have no plans to build on the land in the future. The quickest and most cost effective way to decommission their 4 tanks was to concrete fill them. The great thing with concrete, is that we can use concrete slurry to fill the tanks right up-to ground level, often seamlessly blending the old holes with the current concrete surface.
As you can see from our images, we decommissioned all 4 tanks, blended the empty tanks with the remaining concrete surface.
It is important to note that before we commenced decommissioning work, we thoroughly cleaned out the underground tanks to ensure no dangerous chemicals were left. To find out more about our tank cleaning services please click here.
Here at Bio Clean Jetting Limited we cater for above or below ground fuel storage tanks any size or shape. We provide two types of service: either remove the tank or solid fill the tank (we use concrete).
Get in Touch
Portfolio
More of Our Projects
Check out some more our recent projects below...

Heating Oil Tank Removal from Barston Green Birmingham
Project Details The Bio Clean Jetting team worked a Saturday to fit this project in and ensure our clients were happy. We removed over 1,000 litres of oil to prepare the tank to be removed and disposed of. We then

Large Tank Removal in Birmingham
Project Details We won a contract to remove a 25,000 litre heating oil storage tank from a listed building in Birmingham. This was really no easy task as the tank was located 15 feet above ground level and due to

Large Spillage Prevention
Project Details We were contacted by a new client. They informed us that their domestic property’s heating oil tank had started to leak after being filled. Our companies quick reaction prevented a large spillage occurrence. Once the tanks had been